In the last part, the panels were mounted, EMT was ran between all four enclosures, and the garage was back on temporary power. This post covers the cable trough, moving the circuits out of the old panel, moving the main service into the GridBoss, and the rapid shutdown switch.

Completed July 2026

The work in this post was done between June 22nd and July 26th, 2026. The rapid shutdown switch went in a bit later, and was in place by August 9th, 2026.

Disclaimer - I have been slacking, and the vast majority of the garage has been done for months….

Garage wall at the end of part 2, conduit between the main panel and GridBoss

Here is the wall in the middle of June, right before starting this part. Panels mounted, EMT along the bottom, and the old panel still by the door.

Garage wall in mid-June: 200A panel, subpanel, FlexBoss21 and GridBoss mounted with EMT along the bottom, no wireway yet

But - its time to get this finished.

For a refresher, here is the CAD drawing I created prior to doing any work.

Fusion 360 mockup of the garage wall with all four enclosures, conduit and panels laid out

Installing cable trough

With the panels being completed in the previous part, the next step is to get a cable trough installed.

This took quite a while to get ordered, as most of the local options I had for picking up a wireway were asking 300+$ for a decent sized wireway.

BUT, I did manage to find a suitable product on Amazon.

Wiegmann HS666 - Amazon1

Granted, you do have to buy the endcaps separate.

Hoffman F66GCP1

But, for around 240$ total.. this did the job.

So…. after assembling the trough, I sat it on top of the panels to see how well it fit.

6x6 wireway sitting on top of the panels for a test fit, flush against the ceiling

Satisfied with the placement, I started securing it to the studs using lag bolts, with large washers.

Driving a lag bolt with a large washer through the back of the wireway into a stud

It is flush with the ceiling.

EMT from panels to wireway

Next, I needed to put conduit in place for running wire. Again - I used 2" EMT here, to give PLENTY of room.

I used the same 2" EMT connectors as from previous posts.

Lowes - Sigma ProConnex 2" EMT Compression Connector

2" EMT connectors and a knockout plate sitting on top of the main panel

Tool - Knockout Punch

Generally, this is the part where I show the mechanical knockout punch, making life easy.

Knockout punch threaded through the top of the subpanel

Manual knockout punch kit in its blue case, with dies and the draw stud

And - it did make things easy. Until it broke. The threads eventually galled up, and I was unable to use it anymore. I don't recommend using these with an impact. An impact will destroy them.

Amazon - Manual Knockout Hole Punch Driver1

But - if you use the ratchet, I'm sure these would last quite a bit longer.

I DID end up replacing it with a hydraulic knockout punch, which I picked up from Harbor Freight.

The same concept as this one: Hydraulic Knockout Punch1

Just - a different color, and more expensive for what looks basically the same.

BUT - take it from future me, hydraulic is the way. It works much faster and smoother. If you are making multiple 2" knockouts, it will save a good amount of time.

So… the manual set will work just fine, especially if you are only making a few holes. But, for any serious job, I'd pick the hydraulic one every day over the manual one.

Back to running EMT

After punching out the 1.5" hole on top of the middle panel to 2", I installed the connector.

2" EMT connector installed on top of the subpanel

Check your clearances

Before punching a hole in the top of a panel, check the spacing and clearance for the dead front. The connector and locknut need to clear the dead front, or the cover may not fit.

And then repeated the process for the left panel.

200A main panel with the new 2" connector installed in the top

I used a piece of 2" PVC for mockup, and to determine where to drill a hole into the wireway.

Piece of 2" PVC standing between the subpanel and the wireway as a mockup

Then… cut the conduit, installed the connectors…

Cut piece of 2" EMT held up between the main panel and the wireway

Repeated for the other side, and voila. The race is now in, and we have sturdy conduit.

Garage wall with the wireway on top and 2" EMT dropping into both panels

Do remember to strap your conduit.

Replacing the old panel

Prepping the attic

With the cable trough in place and conduit ran, it was time to start relocating circuits from the old panel to the new panel.

In the attic, I setup a work light and a fan. It was north of 130F for most of the summer… and the moving air really helped.

Stay Hydrated

I did most of this project during the middle of June and July, where temperatures were triple-digits for nearly 3 months straight.

Drink LOTS of water. I was drinking two gallons of water per day, and still borderline dehydrated every night.

Drink. LOTS. of water.

Attic over the garage with a clamp work light hung from the rafters

Since the trough was under one of the pieces of OSB, I had to remove the nails, and slide this piece back a bit.

Attic decking with one sheet of OSB slid back to expose the ceiling above the wireway

I then started carving out sheetrock using a knife. I will be punching a lot of holes into the top of this area, where the NM connectors will go.

You can see all of the cable on the way to the existing panel too - its right up against the back wall.

Sheetrock cut away in the attic above the wireway, with the existing romex bundle along the back wall

Another fan was also added, to blow slightly colder 100F air into the attic…

Yellow shop fan sitting on top of the fridge, pointed up the attic ladder

The old panel

With the attic prepped, I started by removing the sheetrock above the old panel, to make it much easier to loosen and remove the old connectors.

Sheetrock cut away above the old panel, exposing the mass of romex feeding it

And removed the old connectors.

Close-up of the romex entering the top of the old panel with the connectors removed

The cable race did have a collection of knockouts already. However, most of these were larger than the half inch NM connectors I used. BUT, these 3/4" and 1" knockouts worked great for the larger cable.

Top of the wireway from the attic, with NM connectors installed in the existing knockouts

And… as this is before I broke the manual knockout tool - it was working really great for making new holes.

Milwaukee impact driving the manual knockout punch through the top of the wireway in the attic

Off-topic, you might consider wearing sleeves and gloves to move around the old fiberglass insulation. Otherwise, you will be scratching for a few days. A cold shower is the best thing I have found to help remove it.

Pink fiberglass insulation pulled back from around the wireway in the attic

The process of relocating circuits is pretty simple.

  1. Flip breaker off.
  2. Remove breaker.
  3. Try to disconnect the cable from the breaker, neutral & ground bar.
    • Cut the cable instead, because you cannot get to the neutral / ground bar.
  4. Pull the cable up through the attic.
  5. Place a correctly sized NM connector over the cable.
  6. Install into the wireway.

Temp Connection

To power everything in the new panels while migrating cables, I used a temporary feeder connection, wired with 60A breakers and 6AWG cable.

Amazon - Eaton BR260 60A Breaker1

Danger

For many reasons, such as personal liability against electrical shock and/or fire hazards, I don't recommend you do this.

While this cable is drastically undersized to power the entire house, it would work as a temporary connection while I moved the bulk of circuits into the new panel.

Temporary 6AWG feeder landed on a 60A breaker

It was slotted into the bottom right of the old panel, using a 50 or 60 amp breaker.

Old panel, half emptied, with the orange temporary feeder leaving the bottom right

Through this project, I did keep an eye on the amperage, which is important, as this is quite undersized compared to what is needed.

And - don't worry… there was a ground / EGC connected too.

Moving the main power

The main cable feeding my house is 3/0 copper. Its big, bulky, and not fun to bend into tight spaces.

Here is the area I am working with. The GridBoss is on the right side of the wall, and the old panel is in the wall, right next to the door.

FlexBoss21 and GridBoss on the wall, with the old panel opened up in the wall next to the garage door

First - I attached 2" EMT to the bottom-right of the GridBoss. The intention is to go straight out the exterior wall to the right.

2" EMT sweep leaving the bottom right of the GridBoss, headed for the exterior wall

For this project - I have been using EMT on the interior, BUT switching to PVC for the exterior. I did the same here, by using an EMT connector with a female PVC adapter.

(Ignore the white fitting - it has long since been connected!)

Mocking up the run from the bottom of the GridBoss to the hole in the wall, using a PVC elbow

EMT run reaching the hole in the garage wall, with a PVC female adapter on the end

After leveling and flushing the conduit, I drilled a long screw into the centerpoint of where the conduit stopped. Alternatively, you can measure from the outside wall. But - I felt this works just fine.

Long screw driven through the wall at the center of where the conduit ends

And, of course, there is a piece of conduit right in the way of where I need the cable to come in.

Outside the house: the marker screw poking out of the siding, right next to an existing run of PVC

On Friday - the wife and kids were out in town, which made a perfect time to move the main cable over. The first step was to turn off power at the pole, and then TEST to ensure the panel is DEAD.

Afterwards, I disconnected the cable from the lugs.

Main service cable disconnected from the old panel's lugs and pulled out of the wall

On the exterior, I was not happy with how the old conduit looked. It was painted, and kinked where someone used a torch to bend it. I cut below the bend, in a location where I would use a connector to run new conduit which hugs flush against the rock.

Old painted service conduit on the outside wall, kinked where it was heat-bent

And, a few moments later…..

Old service conduit removed, with the service cable hanging loose on the sidewalk

For installing connectors into boxes which I plan on sitting flush on the outside of the house - I use hole saw bits to drill a hole to the size of the connector, allowing the connector to set inside of the wall.

Hole saw bits test-fit against a 2" PVC elbow to find the right size

This is the hole saw set I have been using: Milwaukee 42-22-41851

Also - the same set I used for drilling holes into the panels at my old house too.

I then drilled the holes…

Drilling through the wall from the inside with the hole saw

And started preparing the junction box. As I drilled a very tight hole, I did need to file down the connector to fit into the hole.

Filing down the PVC connector on the back of the junction box

Which - was a very snug fit, on purpose.

Connector pressed snugly into the hole in the siding

For connecting to the junction box, I ended up drilling out the bottom of the box and installing a conduit hub, bolting it into place with silicone to prevent any leaks.

Siemens EC38599 2" Conduit Hub1

2" conduit hub bolted into the bottom of the PVC junction box

Inside of the junction box, showing the hub and the hole for the rear connector

On the back of the junction box, I cemented the connector into place. Overkill, but I will never be removing this, and I don't want it to ever leak.

Rear connector cemented into the back of the junction box

Here is the inside of the box, with everything cemented or siliconed into place.

Inside of the finished junction box with the hub and rear connector sealed

Next up…. the junction box was secured to the house, with a healthy amount of silicone on the rear to prevent any leaks.

Gray junction box mounted on the siding above the rock, next to the other conduit runs

Now, I spent a while playing with various angles to find the most aesthetically pleasing way to enter the house.

After a while, I settled on a pair of 45s, with a short section in the middle.

PVC run from the ground up to the junction box using a pair of 45 degree elbows

Info

The different color bothers me too. It was a piece of the old 2" conduit. At this time, I was out of new 2" PVC.

And… for the fun part. Fighting this 3/0 copper.

3/0 copper service conductors being fed up into the junction box

Cable lubricant is your friend..

Amazon - Gardner Super-Slick Cable Lube1

The neutral leg was not long enough to fully reach the GridBoss.

I did need to use splices here.

Junction box on the siding with the multitap splice blocks test-fit, the new PVC coming up from below, and the old ingress hole to the left

I did use Noalox here, as the new cable I have is 4/0 aluminum. These adapters are copper. And the old cable is copper.

Amazon - Noalox (Anti-Oxidant)1

Amazon - 250MCM -> 6AWG Multitap1

After a fair amount of struggle….. everything was in the junction box.

Junction box on the siding with all of the splices made and folded in, PVC run from the ground below it

On the inside, the feed comes in through the bottom of the GridBoss, and lands on the 200A main breaker.

Amazon - Eaton CSR2200N 200A Main Breaker1

Inside the GridBoss: the incoming service conductors landed on the main breaker, with the EMT from the exterior wall coming in from below

As it was getting dark, I zip-tied a plastic bag around the old ingress, and installed the cover on the junction box.

Junction box with its cover on and the new PVC run complete, at dusk

I did almost step on a copperhead…. gotta watch out.

Copperhead snake on the sidewalk next to a shovel

Romex vs THHN/THWN-2

The plan was to pull the existing romex into the wireway, strip the sheathing, and then transition to THHN/THWN-2 to continue into the panel.

As I really did not want to have a race full of wirenuts, I decided to use DIN-mounted splice blocks.

Two rows of DIN rail terminal blocks with numbered markers, held over my lap

Amazon - 20A/600V Terminal Block1

These are rated for 20A, 600V, and do carry UL certification.

The rest of the DIN hardware:

Assembling junction blocks & preparing cable

I used a cable comb to help organize the cables, and to remove knots. This is a comb primarily used for CAT5/CAT6. But, it worked here too.

Bundle of black, white and green THWN held together with a yellow cable comb

And… for a few hours, I sat here, stripping cable, and attaching labels to each and every wire.

Amazon - Klein Wire Markers1

Handful of stripped THWN conductors, each with a numbered label

This was the end result.

Coil of labeled THWN terminated into a DIN rail of terminal blocks

I did have to do this twice - two blocks in total, 20 circuits.

Then…. I started running a lot of THWN from the breakers to the race.

After which, everything was terminated into the terminal blocks.

Inside of the trough with the lid off: both terminal blocks on DIN rail, romex coming in from the attic on one side, THWN heading down to the panel on the other

Do pay attention - all of the cables are marked on the terminal blocks, and at both the start and end of each piece of cable.

One of the next evenings, I tackled the other half of the panel.

Second batch of conductors run from the main panel up into the wireway

And here is the main panel, fully wired.

200A main panel fully wired, every circuit fed from the trough above through the 2" EMT

More Conduit - Wiring Solar

As a random note - all of this was completed before the first solar panel was ever installed…. despite the solar panels post going up first.

I did bend a few pieces of 3/4" EMT to feed a few circuits.

Pieces of 3/4" EMT bent to run between the subpanel, FlexBoss21 and GridBoss

Mainly - I have the minisplit for my office, and the outlets which needed to be fed to one of the panels.

In addition, I needed EMT for the cables carrying energy from the PV panels.

EMT runs for the PV conductors coming into the FlexBoss21 and GridBoss

I am not an expert (or even remotely good) at bending conduit. Don't judge… I'm aware its bad.

Close-up of my less-than-perfect EMT bends below the GridBoss

I did amass a total of three different conduit benders…. 1/2", 3/4", and 1". I wouldn't bother trying to get by with just one. Each bender only works properly with its own size of conduit.

Removing the old panel

One circuit at a time, the old panel emptied out.

Old in-wall panel with only a handful of circuits left in it

By the middle of July, the new panel was full, and the old panel next to the door was gutted.

Garage wall in July: the new 200A panel full of breakers, and the old in-wall panel gutted next to the brown door

A few weeks later, the old panel was removed. That left a hole in the wall, next to the GridBoss.

Empty cavity in the wall where the old panel used to be, between the GridBoss and the door

I framed in the cavity with a few pieces of 2x4.

Old panel cavity framed in with 2x4s

What goes into this spot will be covered in the next post.

Rapid Shutdown

The last piece on the outside is the rapid shutdown switch (RSD).

The RSD circuit starts at the RSD terminals on the FlexBOSS21's control board.

FlexBOSS21 control board, with the RSD terminals (SW, G, +12, +24), with red wires landed on the SW terminals

From there, it runs through the 1" low-voltage conduit over to the GridBOSS, then to the cabinet on the right of the GridBOSS, and then out through the wall to the shutoff button.

flowchart LR
    FB[FlexBOSS21 RSD terminals] --> GB[GridBOSS]
    GB --> CAB[Cabinet right of the GridBOSS]
    CAB --> SW[Exterior RSD shutoff button]
    SW -.->|normally closed loop| FB

This is a normally closed (NC) circuit. Pressing the button opens the circuit…. and when the circuit is open, everything fully shuts down.

The switch is mounted on the outside of the house, next to the junction box for the main feed, with a sign above it.

Outside wall with the EMERGENCY SHUT-OFF sign, RSD switch, junction box and PVC runs below the mini-split

Close-up of the red RSD switch, the gray junction box and the PVC runs on the siding

Next Steps

None of the sheetrock is done yet.

The next post will cover what went into the old panel's spot, and the monitoring.


  1. Amazon Affiliate Links Used

    This post DOES include Amazon affiliate links. If you found this content useful, please consider buying the products displayed using the provided links.

    You will pay the same amount as normal, however, it does provide a small benefit to me. This benefit is usually used to purchase other products and hardware for which I can review / blog about.
    
    I do not display advertisements on this site. As such, the only compensation from this service, comes from affiliate links. I do not ask for, or even accept donations. 
    

    ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩